Name of the work:- Repair and maintenance of existing Nullah at Sucobhatt Moddi, Navelim, Salcete Goa.
The work started from 04/04/2016. Total man days generated 336. Total beneficiaries, six females & one male, with the total strength of 07 daily wage workers. Total wages paid is Rs. 82,669/-. The cost of material is Rs. 40,400/- and administrative cost is Rs. 6780/- Total Expenditure Rs. 1,29,849/-
The above mentioned work has been fully completed in good condition as on 12/06/2016.